Last Updated on: 14th Apr, 2023
Sl. No. | Item | Details | Underprogress | Completed | Untackled |
---|---|---|---|---|---|
1 | Upto SG TopĀ | 24 Kms | 6.28 Kms | 17.32 Kms | 0.400 Kms |
2 | GSBĀ | 24 Kms | 6.49 Kms | 17.11 Kms | 0.400 Kms |
3 | CTB & WMM | 24 Kms | 7.42 Kms | 16.18 Kms | 0.400 Kms |
4 | DBM | 24 Kms | 9.61 Kms | 13.99 Kms | 0.400 Kms |
5 | BC | 24 Kms | 0 Kms | 0 Kms | 0 Kms |
6 | Service / Slip Roads Length | 10.169 Kms | 0 Kms | 0 Kms | 10.169 Kms |
7 | Major Bridges | 10 Nos | 3 Nos | 7 Nos | 0 Nos |
9 | Minor Bridges | 8 Nos | 2 Nos | 6 Nos | 0 Nos |
8 | Vehicular Underpasses | 1 Nos | 1 Nos | 0 Nos | 0 Nos |
10 | Light Vehicular Underpasses | 6 Nos | 0 Nos | 6 Nos | 0 Nos |
11 | Interchange Structures | 4 Nos | 4 Nos | 0 Nos | 0 Nos |
12 | Ramp Plazas | 5 Nos | 0 Nos | 0 Nos | 5 Nos |
13 | Box Culverts | 76 Nos | 2 Nos | 71 Nos | 3 Nos |
14 | Pipe Culverts | 37 Nos | 0 Nos | 9 Nos | 28 Nos |
15 | Longitudinal Drains | 61 Kms | 0 Nos | 0 Nos | 61 Kms |
16 | Boundary Wall | 48 Kms | 15 Kms | 5 Kms | 28 Kms |